Villiers Primary School – IKO ULTRA Gold 20
Project description
IKO Technical representatives carried out a full roof survey of the flat roof areas of the school and carried out a number of cores samples upon each area to ascertain the existing waterproofing build-up.
In consideration of the need to maintain the waterproofing integrity, sampling was kept to a minimum.
ISSUES IDENTIFIED
Water ingress.
Large repair needed to hall roof.
Previous workmanship very poor.
Roof lights fragile, UV damage and liquid repair previously done.
Huge splits and blisters.
Asphalt slumped into gutter.
No flame free zones.
SOLUTION
Rooflights replaced.
Windows raised to achieve the minimum upstand height of 150mm.
Overlay a new high performance bituminous system.
Thermal upgrade using IKO enertherm PIR Tapered Insulation.
RESPONSIBILITY
Customer made aware of evidence of internal damage to decoration in several areas and confirm whether these are historic stainings or ongoing.
PRODUCT/SYSTEM
IKO ULTRA Gold 20 Warm Roof System.
IKO Superlite Modular Rooflights.
IKO Refurbishment Outlets.
IKOtrim.